A mine is healthy when it digs what it planned, safely, at a sensible cost, and can ship it. Each vital sign needs its own data. The tags show what we have covered so far.
Output
Did we dig the planned coal?
CoveredMovement
Did the coal leave: road, rail, stock yard?
CoveredMachines
Are shovels, dumpers and the surface miner working?
Partly: breakdowns only, not hours or idle timePeople and safety
Enough operators? Is the pit safe?
Not yetQuality and cost
Right grade? What does a tonne cost?
Not yetSurroundings
Weather, power, water, railways, community.
Partly: weather and rakes2. Every data source, in plain language
Trust level: how much you can rely on it alone, before cross-checking.
| Source | What it tells you | Best reliable way to get it | Trust |
|---|---|---|---|
| Covered in version 1 | |||
| Production plan and actuals (SAP) | How much coal we meant to dig versus how much we dug. | Scheduled nightly extract arranged with SAP and IT. Cross-check against survey or stock measurement. | High for totals. It never says why. |
| Dispatch (Coalnet: RFID, weighbridge, rakes) | How much left the gate, by road or rail, and to whom. Shows queues and rake delays. | Scheduled extract from SAP/Coalnet owners. Machine-recorded, so the most dependable source. | High |
| Shift reports (paper) | The shift’s own story: output, machines working, problems faced. | Photo at shift end, then OCR. An officer checks a sample. Keep paper as the legal record. | Medium. Handwritten, often incomplete. |
| WhatsApp groups | Live events with timestamps: breakdown started, rain began, rake placed. | Export now, company business number later, own app eventually. AI extracts, humans confirm doubtful items. | Medium-low alone, strong once matched with other sources. |
| Meetings (evening and morning) | Priorities, decisions, who owns which action. | Record with consent, transcribe, manager approves the minutes. | Medium. Decisions need approval before they count. |
| Phone calls | Verbal escalations: spares, railway, urgent fixes. | Mostly invisible today. Ask officers to log a short voice note after key calls. | Low until logged. |
| Weather | Rain stops work and wrecks haul roads. | On-site rain gauge plus a weather service. Easy and automatic. | High |
| Equipment list and breakdown log | Which machine failed, when, why, what fixed it, whether it came back. | Maintenance register or SAP maintenance records, linked to the chat events. | Medium-high |
| Next to add | |||
| Machine hours and fleet tracking (GPS or fleet system, if installed) | Where time is truly lost: waiting, queuing, idle, travel. | Hour meters and fleet-management exports; otherwise a simple shift sheet. | High if automatic |
| Manpower and attendance | Do we have enough trained operators today? | Attendance or HR system, plus contractor muster. | Medium-high |
| Spares and stores | Why a repair is waiting: part not in stock. | Stores and inventory system extract. | High |
| Safety and statutory records | Incidents, near misses, inspections, slope or ground movement, gas, dust. Whether it is safe to keep working. | Safety registers and monitoring systems, strictly permissioned. The AI stays advisory only. | Medium. Under-reporting is common. |
| Later | |||
| Drilling, blasting and overburden removal | Is coal exposed for tomorrow? A leading indicator of future output. | Blast and drill records, survey measurements. | Medium-high |
| Survey and mine plan | Where the coal is, how deep, how much waste rock to move per tonne. | Survey department files and plan drawings. | High |
| Coal quality (grade, ash, moisture) | Whether coal is sellable at the promised grade. Affects revenue and rejections. | Lab and sampling reports, including third-party samples. | High if sampling is sound |
| Fuel, power and pumping | Diesel efficiency, power cuts, water in the pit. | Fuel logs, power records, pump and sump readings. | Medium |
| Rail and customer demand | Whether anyone can take the coal: rake availability, orders, auctions. | Dispatch cell, railway and sales records. | Medium-high |
| Cost per tonne and contractors | Is it economical? Are hired machines delivering? | Finance and contract records. | Medium |
| Outside disruptions | Land, community, law and order, clearances, environmental limits. | Manager’s log; hard to automate. | Low, but matters |
3. How to get data you can trust
1. Machines beat people
Rank sources: sensors, then system transactions (SAP, Coalnet), then forms, then chat and voice, then memory. Lean on the top of the list.
2. Capture once, at the source
No retyping. Every retyping step adds errors and delay. This is why the future app matters.
3. Two sources per claim
Output from SAP should roughly match dispatch plus stock change. A breakdown in chat should appear in the maintenance log. Mismatches get flagged, not hidden.
4. Keep the evidence link
Every structured row points back to the original message, photo or record so a manager can check it.
5. Humans verify the doubtful bits
The AI marks its confidence. Only low-confidence items go to a 10-minute daily review.
6. Start small and permissioned
Ask for a limited, approved extract per source for one mine. Written permission first, then data.
4. How the sources connect
Everything joins on a few shared keys. If these are clean, the sources fit together like a puzzle. If they are messy, nothing matches.
Worked example: 10,000 t planned, 8,000 t actual (synthetic data, 18 Sep)
| Source | The clue it gives |
|---|---|
| Plan and SAP | Planned 10,000 t, produced 8,000 t, so 2,000 t short. Nothing about why. |
| Shift reports | B shift notes “hose burst” and “rain”. A shift mentions the late rake. Some details missing. |
| Breakdown log | EX-03 hydraulic hose burst, 15:10 to 20:40. |
| Weather | 38 mm of rain, 17:30 to 21:00, overlapping the breakdown. |
| Coalnet | Rake placed about 4 hours late, so dispatch fell. |
| Exact timestamps for when each thing started and ended. | |
| Past incidents and manager notes | Same hose failure recurred through Jul–Sep (most recently 1 Sep); experience says hoses fail more in heavy rain. |
5. How decisions are made in a mine, day to day
The logic never changes: what we owe (target) compared with what we can actually do (machines, people, weather, roads, rakes, buyers), minus what is blocking us. Every shortfall should get a reason and an owner.
Is the shift ready?
Officials check the workings and safety, confirm which machines are fit and how many operators are present, brief the crew, and receive the day’s programme. Decides: shift in-charge and mine officials.
Keep coal moving
Assign machines to faces, manage the haul cycle, react to breakdowns (move a shovel, call maintenance), stop or restart for rain, manage weighbridge queues and rake loading. Decides: shift in-charge, minute by minute.
Handover
Output, open problems and pending jobs are handed to the next shift and written in the report.
What went wrong yesterday?
Review target versus actual, name the causes, assign fixes with owners and deadlines. Decides: manager with mining, maintenance, dispatch and safety.
Fix and prepare
Schedule maintenance, drilling and blasting, spares, and rake and road dispatch with the railway and customers. Stock yard level shapes how hard to cut versus how hard to dispatch.
Set tomorrow’s programme
Fix the target, face and machine allocation, dispatch priority, maintenance windows and safety jobs, using weather and rake forecasts and open breakdowns. Decides: manager, approved by senior officers.
Bigger resources and targets
Compare monthly target with achievement, request equipment, manpower or funds from area or headquarters, and report upwards.